page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138 page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
136 CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
The design flow of this micro-hydro scheme is 401/s and the
intake is shown in Photograph 10.1.
Over a six month period, the performance of the screen has
shown the following characteristics:
Around 90% of sediment between 0.5 mm and 1 mm
diameter was excluded.
Some build up of algae was noted, but this did not inhibit
flow during the trial period.
The effect on performance due to ice was not noticeable,
even at temperatures 12°C below freezing point.
Tests are required over a longer period to check for corrosion
of the screens and effect of continued algae growth, particularly
in warmer temperatures.
More information on Coanda screens can be obtained
from:
DULAS Limited,
Machynlleth, Powys SY20 8SX, Wales, UK
Fax: +44(0)1654781390
e-mail: dulas@gn.apc.org
A pilot project in Nepal, a Coanda screen has been retrofitted
in an existing micro hydropower plant with joint efforts by
Small Hydropower Promotion Project (SHPP/GTZ), Energy
Systems and Rural Energy Development Program (REDP) of
United Nation Development Program (see Photograph 10.3).
Dulas Engineering provided the Coanda Screen at free of cost
for this pilot project.
A 16 kW Cha Khola micro-hydropower plant at Singe VDC,
Kavrepalanchowk district, Nepal was identified to be suitable
for retrofitting the Coanda screen. It was agreed that the ideal
location to retrofit a Coanda screen would be at the forebay of
this micro-hydropower plant. Major specifications of the Cha
Photo 10.2 Weld beads on HDPE surface
Photo10.3 De-beader tool
Khola micro hydropower plant are as follows:
Design Flow: 50 l/s
Gross Head: 55 m
Installed Capacity: 16 kW
Turbine: 3-jets Pelton
Beneficiaries: 125 Households
Screen commissioning
During commissioning in January 2004, the screen operation
was observed until a steady condition was reached. Once,
steady state was reached, the turbine nozzles were closed to
observe the overflow/spilling mechanism from the screen.
Some leaves, stems and twigs were introduced into the flow
to observe the self-cleaning mechanism of the screen. Also, a
handful of sand particles were placed at the weir crest of the
screen during the steady state flow condition to visually observe
the sediment exclusion effects.
The findings during the commissioning phase were as
follows:
i. When leaves, stems and twigs were introduced with the
flow, they initially blocked part of the screen openings.
However, the entire diverted discharge was able to pass
through the screen even when the flow was partially
obstructed. When the turbine valves were closed, the water
flowing through the screen pushed the leaves out (of the
screen), demonstrating the self-cleaning mechanism.
ii. Although it was not possible to visually quantify the
sediment volume that passed over the screen when such
sediments were introduced at the weir section, the larger
once could be seen rolling down the screen.
iii. The discharge entering into the screen passed through
the first 250 mm to 300 mm length (the screen length
is about 645 mm).